Rate Case Roundup: Oregon
Portland General Electric was authorized a rate increase of $15.9 million out of $99.9 million sought.
In a proceeding in Canada before the Ontario Energy Board, the board permitted an electric transmission service company, Five Nations Energy Inc., to raise its base revenue requirement from $6.33 million to $7.84 million for 2017. The revenue requirement for 2018 was augmented by a further $150,000 to account for expected staffing costs and changes in cost of capital.