ETC

Transmission Tug-of-War

From EPAct to Order 1000, siting authority continues evolving.

Six years after Congress granted FERC “backstop” siting authority for electric transmission projects in the Energy Policy Act of 2005, the regulatory landscape is still evolving as a result of federal court decisions and new FERC orders. But despite a lack of certainty at the federal level, project sponsors have filed numerous applications at the state level for new transmission projects. Can these projects proceed without greater certainty at FERC?

Bench Report: Top Ten Legal Decisions of 2011

1. ‘Policy’ Guides the Grid; 2. Carbon Not a Nuisance (Yet); 3. Gigabucks for Negawatts; 4. A MOPR, Not a NOPR; 5. Ramp Up the Frequency; 6. Cap-and-Trade Still Lives; 7. Cyber Insecurity; 8. Korridor Killer; 9. The Burden Not Shared; 10. Ozone Can Wait.

Vendor Neutral

(June 2011) Duke and ATC team up to build transmission lines; AEP installs bioreactor to control selenium emissions; NextEra buys 100 MW of wind from Google; Ocean Power Technologies awards contracts for wave power array; Kansas City picks Elster; BC Hydro picks Itron; plus contracts and developments involving Tres Amigas, Ioxus, Opower and others.

The Queue Quandary

Why developers today are often kept waiting to get projects ok’d to connect to the grid.

Late last year FERC learned that the Midwest regional grid likely would require at least 40 years — until 2050 — simply to clear its backlog of proposed gen projects awaiting a completed interconnection agreement to certify their compatibility with the interstate power grid. But grid engineers would meet that date only by shortening the process and studying multiple projects simultaneously in clusters. To apply the process literally, studying one project at a time, as envisioned by current rules, the Midwest reportedly would need 300-plus years to clear its project queue.

Vintage, Voltage or Votes

AEP rekindles debate over grid pricing, but should the outcome hinge on majority rule?

You might have thought the Feds closed the book on any broad, region-wide sharing of sunk transmission costs—especially after FERC ruled last spring in Opinion No. 494 that PJM could stick with license-plate pricing (LPP) for transmission lines already planned and built. If you thought that, you weren’t alone. Of 25 transmission owners (TOs) in the Midwest ISO (MISO), 24 voted recently to do the same for their market as well.

Transmission Line-Siting Under EPACT: Shortcut or Short Circuit?

The 2005 Act, designed to streamline projects, may fall short of that goal.

The Energy Policy Act of 2005 was supposed to streamline the siting process and provide a federal “trump card” for projects delayed at the local level, but it is far from clear whether these goals have been, or will be, achieved.

PJM Addresses Local Supply Issues

Electric shortages and the generation overbuild continue to co-exist.

While maintaining its stance as the most sophisticated competitive electricity market in the country, PJM still faces several challenges, all of which are augmented by its expanded footprint. Most prominent is the RTO’s plan to implement a new reliability pricing model. Further, parts of PJM are ailing from transmission congestion issues that limit access to abundant, cheap power sources in the region.

CIOs Under Pressure

IT officers are getting more efficient, but guess what keeps them up at night?

Ever-present security concerns are keeping utility chief information officers up at night. With their IT budgets under constraints in a back-to-basics era, four CIOs speak out about their concerns over funding, staffing, and the future.

Another Food Fight!

The new transmission siting and permitting policies could be just as messy and unruly as the old ones.

The idea behind the NIETC is a noble one: to help facilitate the construction of badly needed transmission capacity to relieve congestion problems and improve reliability. In fact, the promotion of new infrastructure investment is at the heart of EPACT. But there’s just one problem. The new process for permitting and siting electric transmission under EPACT appears to be as flawed and contentious as it was pre-EPACT.

Kicked Off and On Schedule

Cal-ISO files a new market design, but has it traded efficiency for software?

Eyeing a launch date of November 2007, Cal-ISO at last has come forward with plans for revamping its widely disparaged wholesale market design. The formal proposal, known as the MRTU (Market Redesign and Technology Upgrade), was filed this past February at FERC.