Pa. Court Defines Need for Transmission Lines
Overturning a utility commission ruling, the Pennsylvania Commonwealth Court has concluded that state law does not require an electric utility to prove that a planned transmission facility is needed from an engineering perspective to win a certificate of convenience authorizing construction.
The court overturned a ruling by the Pennsylvania Public Utility Commission that had denied an application by Pennsylvania Power and Light Co. to construct a 69-kilovolt transmission line.