Alstom signed a €250 million contract with Metals & Engineering Corp. (METEC) to supply turbines and generators for the hydro power plant of the Grand Renaissance dam, located on the Blue Nile in Ethiopia. Alstom will supply and supervise the installation of all electromechanical equipment for the plant, including eight 375 MW turbines and eight generators for the first phase. The contract also includes engineering and power plant commissioning, scheduled to start in late 2013 and finish in 2016. When completed, the 6,000-MW Grand Renaissance power plant will be the largest hydro project in Africa.