ABB was awarded a contract by Atlantis Resources Limited to provide the onshore grid connection for Phase I of the MeyGen tidal stream project in Scotland's Pentland Firth. The first 6-MW demonstration phase of the UK's first large-scale tidal array scheme will see four submerged turbines installed in the Inner Pentland Firth just north of Caithness, with first power expected to be delivered by 2016. ABB is responsible for the onshore power conversion and grid connection systems to feed the electricity into the local distribution grid. ABB's project scope includes design, engineering, supply and commissioning of the power conversion, switchgear and transformer solution as well as associated civil engineering and cabling works.